Pages

2 Mar 2017

Fire, Toilet, Shower, Upstairs Wardrobe, Painting, Lights.

As the title suggests, lots to bring you up to date on, as it seems this is becoming a monthly update...
The departure of the joiner was followed by a couple of weeks of low action as Jaimin was busy with work.

Excitingly, especially in the middle of winter, the plumbing was brought to a point where the water could be filled in to the thermal store. Here is the overflow tank filling up.



This meant that the fire could finally be lit! And after a bit of air-block sorting, the famous copper towel radiator even started to work. Result!


With a little help from James, Jaimin managed to install the toilet, box it off, and paint the surround. Finn and Jack were particulary pleased.




 The arrival of Liz (daycare) and Blair (extra pair of hands with experience) meant that some real progress could be made all over the place. The first thing was the shower. The sequence of photos shows the screeding, laying the tray, building the step, waterproofing with liquid plastic and tape (tanking), tiling, and finally grouting.















While this was ongoing, the upstairs wardrobes were also started. These are a partition between the bedrooms, shelving space for the children, clothes storage for us, and a doorway. They frame and the partition section are complete, but the shelves and doors are still on the list.



Also ongoing was the Great LED Experiment. Due to the lack of head height, and the absolute conviction (from Bumpy) that no lighting should allow the viewing of the point source of light (it's a good point...), we designed the upstairs lighting system with LED strips to be stuck to custom made battens, and covered with coverboards. Mr DeWalt, our new friend on site courtesy of our kind neighbour Pete, enabled us to rip 12mm lining boards in to 12x12mm battens, and also make 45degree mitre cuts along the edges of the 12mm boards to create covers. The battens were fixed at 300mm centers with 30mm crews (pilot holes used, obvs) onto which Everbuild Mammoth Double Sided Tape was fixed (if you ever need really good sticky tape...). The LED strips were then fitted, and the cover boards fixed over the top... The results are really pleasing, but hard to photograph well... 



The final thing to update is also lighting related, but is the fabrication of the "pan rack" to go above the island. This was the subject of many design iterations but was agreed to be made as per the photos. Basically, make a ladder, drill some holes, fit some broom handles, and route out a strip all around it in which to stick LED strip lights to light the island...!





There was also painting going on, as Lucy had time to attend the cottage as opposed to being a carer... Liz took on that role very nicely. Here is proof:



(The electrician has also made a brief appearance but not enough to make anyone excited. Next week there should be more on this, and the landscaping...)


25 Jan 2017

"Heat Leak" Towel Radiator

The bathroom radiator is a unique and interesting one. It has been a long thought out project, has taken a lot of planning, and is a quirky idea which we thought would be good for a few reasons. As with all these things, they are at the same time uncomplicated and also very difficult, in some paradoxical way.

The purpose of the radiator is to be "permanently losing heat" when the fire is on, to decrease the chance of a run-away solid fuel fire boiling the water in the back boiler. The capacity of the radiator needs to be 10% of the stove, in our case 1kW for the 10kW output, which is a significant amount. With 17m of non-insulated 28mm copper pipe, this should be met with a temperature difference between the water and the air of around 70 degrees C. 

The mountings are brass munsen rings, screwed in to the wall posts with 5 x 70mm screws (many thanks to the Joiner for sundries). The whole thing is removable via 2 compression fittings at each end, and there will be a bottle air vent trap at the top just in case it's required. There will also plan to be an immersion element in the bottom in case the radiator heat is needed but the fire is not needed/wanted.

The towel hanging and clothes hanging space should prove very valuable... 

Here is some of the build, with thanks to Auren for lending a hand.

Initial weld of L-sections, so that angles were not welded in error which would translate across the radiator.

Pre-second welding, setting out all the pipe and connections with the L-sections

New Zealand plumber, holding our ingenious heat shield  - slates stuck to plasterboard. This is during the final weld.

Kitchen Installation

With Alastair on site, we decided to have him take on the kitchen next. He has installed hundreds, and with 19 years experience we couldn't go wrong.

Setting out the island and the units
The "cladding" goes on
Preparing the worktops
Sash clamps holding the 2 pieces together on the island

Cutting out the sink unit

"The jig", square and sash clamps... and the mini grips. Useful stuff!

Squaring up. (Run 1).

All done


Lovely finishing on the worktops thanks to Alastair's keen eye. 

Flooring

Alastair and Jaimin have installed the flooring - 13.5/3mm engineered oak boards, brushed and oiled, fitted with a click-lock system. 13.5mm is the total board thickness, 3mm refers to the layer of real oak on the top of the floor board. Once it was laid, Jaimin oiled it with Osmo Polyx Matt hardwood oil. Once coat on Saturday and one on Sunday, to protect the floor and prolong the life of the wood.

In the beginning...




In the end...



16 Jan 2017

I want to live in a house with an upstairs

Finn is intent of having a house with an upstairs, given that we are currently in what the grown-ups call a "bungalow". So Alastair (local joiner who did the plastering) has been on hand to push things along. We now have pine stairs fitted, which came as a pre-fab kit from StairWorld.com.







New Year, new paint

It's been quiet at Broombank for a few weeks. Jaimin has been working offshore, then Christmas and winter happened which meant little was done. Lucy managed to paint the upstairs in full, leaving downstairs to be painted over the past week. This was completed on Sunday by Lucy and special guest star Heidi. During the past week Lucy, Jaimin and the kids(!) have managed to team up and get it all covered.

Bare plaster paint was applied to the mare plasterboard walls. This was painted over with a single coat of Valspar Matt Putty White. The ceiling was painted with Cuprinol Pale Jasmin, one coat on the boards and 2 on the joists. This was the same in the bathroom although the boards received 2 coats. The kitchen wall was coated in Valspar Matt in "Gina's Eyes" blue/grey.

Very good team of painter